DREDGING ROUNDUP

April 12, 2018

It’s been a busy winter for the Jenkins Dredge team…

 

Since the 300m3 split hopper barges ‘Nab and Needles’ returned from Scotland in September 2017 they haven’t stopped! The backhoe dredger ‘Doreen Dorward’, and split hopper barges

 

‘Nab and Needles’ started a maintenance dredge in September for Dean and Reddyhoff Marinas at Haslar Marina (just inside Portsmouth Harbour entrance, and opposite the iconic Spinnaker tower), of over 30,000m3. Spoil had to be loaded and transported to sea near the Nab Tower disposal ground off the Isle of Wight. This was completed in November, and followed by some vessel maintenance works back in Poole.

 

Early December saw us start work in Plymouth for the Yacht Haven’s group using our new 48t long reach excavator. Dredging was required to bring sea

bed levels back to original depths at Plymouth Yacht haven, Yacht Haven Quay and Turnchapel Wharf, with an estimated total dredge of 75,000m3. Disposal of dredged spoil is to the newly opened Plymouth Deep sea disposal site outside the approach to Plymouth Sound, which has been closely monitored by the MMO (facilitated by AIS tracking devices on all Jenkins Vessels).

 

Works here are still ongoing in Plymouth, and due to be completed just before Easter 2018, ready for the start of the boating season!

T: +44 (0) 1202 668558

E: office@jenkinsmarine.co.uk

www.jenkinsmarine.co.uk

Share on Twitter
Please reload

Recent Posts

November 14, 2019

Please reload

Archive
Please reload

Search By Tags

I'm busy working on my blog posts. Watch this space!

Please reload

Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Dockyard Magazine is produced by Crystal Design & Media Ltd (No. 07640081)
Tel: +44 (0)1634 568925
E-Mail: digital@crystaldesignandmedia.com